THE PREVIOUS STAGE 4 EMERGENCY CONDITION HAS BEEN RESCINDED
Stage 4 Emergency Condition
System Outage due to Doc Curb Pump Failure # 2
CENTRAL TEXAS WATER SUPPLY CORPORATION
P.O. BOX 2393
HARKER HEIGHTS, TX 76548
(254)698-2779
1-23-24
Central Texs Water Supply Corporation has Pump #2 failure at the Doc Curb Water Treatment plant. Pump #1 is still being repaired.
Reduce and maintain daily water demand at or below 25% of system or isolated area's capacity. Begin additional water reductions to wholesale customers and implement water rate surcharges for excessive use of water. Notify TCEQ.
We are looking at all options for repairs. Estimated time for repair is one week.
ALL CUSTOMERS OF THIS CORPORATION ARE AFFECTED
Lee Kelley
General Manager
Stage 2 Drought Warning
Moderate to Severe Conditions
Drought Conditions – Low Lake Levels
CENTRAL TEXAS WATER SUPPLY CORPORATION
- O. Box 2393
HARKER HEIGHTS, TEXAS 76548
Office: (254)698-2779
8/8/2023
All customers of the Corporation are AFFECTED
Central Texas Water Supply Corporation is initiating Stage 2 Drought Warning Moderate to Severe Conditions - Water Rationing due to severe drought conditions and low lake levels. Begin water reductions to customers, require wholesale customers to implement alterative water supply sources and consideration of limiting nonessential water usage. Reduce and maintain daily water demand at or below 90 percent of system capacity. Customers are asked to restrict/ration water usage.
Stage 2 may be rescinded when conditions improve.
CENTRAL TEXAS WATER SUPPLY CORPORATION
- O. Box 2393
HARKER HEIGHTS, TEXAS 76548
Office: (254)698-2779
6.28.23
Central Texas Water Supply Corporation has been working on Pump #2 at System Split. Pump #2 has been rebuilt, parts were not available and have been on order for several weeks. The motor will be delivered and installed on Friday, June 30.
Reduce and maintain daily water demand at or below 80% of system or isolated area’s capacity. Begin additional water reductions to wholesale customers and implement water rate surcharges for excessive use of water. Notify TCEQ.
It may take 10 days to one month for the system to catch up with water demand.
The customers of the Corporation AFFECTED are:
B-M-F, Bell County WCID #5, Little Elm, Salem-Elm Ridge WSC,
Town of Buckholts, East Bell WSC,
City of Lott, O & B, City of Rogers, Rosebud Lott ISD,
City of Rosebud, Westphalia WSC
Please let us know if you have any questions.
Thank you,
Lee Kelley
General Manager
Stage 2 Drought Warning
August 08, 2023
Stage 2 Drought Warning
Moderate to Severe Conditions
Drought Conditions – Low Lake Levels
CENTRAL TEXAS WATER SUPPLY CORPORATION
- O. Box 2393
HARKER HEIGHTS, TEXAS 76548
Office: (254)698-2779
8/8/2023
All customers of the Corporation are AFFECTED
Central Texas Water Supply Corporation is initiating Stage 2 Drought Warning Moderate to Severe Conditions - Water Rationing due to severe drought conditions and low lake levels. Begin water reductions to customers, require wholesale customers to implement alterative water supply sources and consideration of limiting nonessential water usage. Reduce and maintain daily water demand at or below 90 percent of system capacity. Customers are asked to restrict/ration water usage.
Stage 2 may be rescinded when conditions improve.